ID Task
Mode
Task Name Duration Start Finish
1 MODELO ESTATICO Y DINAMICO HOLLIN CAMPO YURALPA 165 days Mon 05/03/12Tue 23/10/12
2 MODELO GEOLOGICO 51 days Mon 05/03/12 Tue 15/05/12
3 Modelo Sísmico-Estructural 35 days Mon 05/03/12 Fri 20/04/12
6 Generación...
More
ID Task
Mode
Task Name Duration Start Finish
1 MODELO ESTATICO Y DINAMICO HOLLIN CAMPO YURALPA 165 days Mon 05/03/12Tue 23/10/12
2 MODELO GEOLOGICO 51 days Mon 05/03/12 Tue 15/05/12
3 Modelo Sísmico-Estructural 35 days Mon 05/03/12 Fri 20/04/12
6 Generación de Modelo Estructural (Structural Modelling) 11 days Fri 20/04/12 Mon 07/05/12
8 Modelo Petrofísico (Petrophisic model) 31 days Mon 05/03/12 Mon 16/04/12
12 Análisis Sedimentológico 26 days Mon 05/03/12 Mon 09/04/12
17 Modelo de Facies (Facies Model) 16 days Mon 09/04/12 Mon 30/04/12
20 Distribución de Propiedades (Property Model) 11 days Mon 30/04/12 Tue 15/05/12
22 MODELO DINAMICO 159 days Mon 05/03/12 Mon 15/10/12
23 Validar Datos K, Kr and Pc (Perm / Capilary pressure), con cores 6 days Mon 05/03/12 Mon 12/03/12
24 Saturaciones y Mojabilidad (Saturations and Wettability) 6 days Mon 12/03/12 Mon 19/03/12
25 Validar PVT 4 days Mon 19/03/12 Thu 22/03/12
26 Control de calidad y reinterpretación de presiones (QC and Pressure evaluati